A bill to reinstate and extend the deadline for commencement of construction of a hydroelectric project involving Clark Canyon Dam.

(Sec.1)This bill authorizes the Federal Energy Regulatory Commission (FERC), upon request, to extend for up to six years the time period during which construction must commence on the Clark Canyon Dam Hydroelectric Project located on the Beaverhead River in Beaverhead County, Montana.

Additionally, FERC may reinstate the construction license if it is expired.

Placed on Senate Legislative Calendar under General Orders. Calendar No. 131.

Sen. Daines, Steve [R-MT](R-MT)Sponsor
3 cosponsors1 D2 R
3cosponsors1committees6actions6subjects
  1. Calendars

    Placed on Senate Legislative Calendar under General Orders. Calendar No. 131.

  2. Committee

    Committee on Energy and Natural Resources. Reported by Senator Murkowski with an amendment in the nature of a substitute. With written report No. 115-101.

    Energy and Natural Resources Committee
  3. Committee14000

    Committee on Energy and Natural Resources. Reported by Senator Murkowski with an amendment in the nature of a substitute. With written report No. 115-101.

    Energy and Natural Resources Committee
  4. Committee

    Committee on Energy and Natural Resources. Ordered to be reported with an amendment in the nature of a substitute favorably.

    Energy and Natural Resources Committee
  5. IntroReferral

    Read twice and referred to the Committee on Energy and Natural Resources. (Sponsor introductory remarks on measure: CR S1579; text of measure as introduced: CR S1580)

    Energy and Natural Resources Committee
  6. IntroReferral10000

    Introduced in Senate

Jun 8, 20171

(Sec.1)This bill authorizes the Federal Energy Regulatory Commission (FERC), upon request, to extend for up to six years the time period during which construction must commence on the Clark Canyon Dam Hydroelectric Project located on the Beaverhead River in Beaverhead County, Montana.

Additionally, FERC may reinstate the construction license if it is expired.

Mar 2, 2017

This bill requires the Federal Energy Regulatory Commission, upon request, to reinstate the construction license for the Clark Canyon Dam Hydroelectric Project located on the Beaverhead River in Beaverhead County, Montana.

Construction on the project must commence within three years.

A bill to reinstate and extend the deadline for commencement of construction of a hydroele… — Informed